ZONING
BOARD OF ADJUSTMENT
Minutes-----19 September
PRESENT: M.
Mansouri,
Note: These minutes are unapproved and will be
reviewed on 17 October 2007 for errors, omissions and corrections.
The meeting was called to order at 7:30pm.,
following a site visit to the Frank W. Whitcomb property on
CONTINUED
PUBLIC HEARING: Frank W. Whitcomb
Construction Corp., by Richard A. Fraser, One Source Properties &
Permitting, LLC., Gravel Pit Permit Application.
Ms. Mansouri resumed the continued public
hearing, and noted that Mr. Webb and Mr. Calhoun were appointed at the original
hearing to vote on this matter, along with Ms. Galloway-Leclerc, Ms. Weber and
Ms. Mansouri. Mr. Webb and Mr. Calhoun
changed seats with Mr. Carignan and Mr. Britton, to reflect their voting status
in this matter. She asked for further
comments from members of the public or the Board following the site visit. Ms. Frankiewicz
reported the EPA says that blue herons, spotted lizards and protected turtles
use the wetlands on this site. Mr.
Fraser said he would have to hear from the EPA about them. Peter Palmiatto, a
member of the Walpole Conservation Commission said the presence of protected
species on a project area is a problem.
I f a nearby wetland is impacted, a wetland
permit would be required. Mr. Fraser
said that the project did not meet the criteria for a wetland permit, and that
the wetland would not be impacted. Lou
Shelley of the Walpole Conservation Commission asked how many square feet in
the project area. Mr. Calhoun replied
the plans show 86,016 square feet. Mr.
Shelley said a wetlands permit is needed for 20,000 square feet. Mr. Fraser
said that none of the project area is in the wetland. Mr. Shelley said that any pond requires a
permit. Mr. Fraser said that was
incorrect.
Mr. Palmiatto said
that the wetlands adjacent to the project area have been identified by the
Walpole Conservation Commission as the
Mr. Palmiatto
explained that the wetland has not been registered with the state, but
according to the fourteen evaluation criteria used by the town Conservation Commission, this wetland had the highest rank within the
town. The paperwork was not submitted to
the state because the private landowners did not want that. The Conservation Commission’s position is
that work next to a wetland should have a state permit. Mr. Sisson replied that the state does not
have a permit for this situation. It is
an issue for zoning. Mr. Palmiatto said that he does not know if this project will
have an impact on the wetland. Putting
in an application will help determine what impact there will be.
Mr. Calhoun relayed remarks made to him on
the site visit by Duncan Watson, who was unable to come to the hearing. Mr. Watson was concerned about the condition
of the site and management of materials on the site. Unmarked barrels were on the site adjacent to
the wetland. He is concerned about
possible impact on both the wetland and the proposed pond. Mr. Fraser noted that the site is used for
construction material storage. Bill Ballou, of FWW, explained that no hazardous waste or
gasoline is stored there. After the
construction season is over, the site is cleaned up. Mr. Shelley said that FWW had a wetlands
violation within the last ten years where materials leaked into a wetland. Ms. Weber said that although the storage site
was not part of this application, the site visit caused her to wonder if, over
time, rain on the stored materials could cause leachate
into both the proposed pond and the existing wetland. Mr. Fraser said that the storage area is a
separate issue. He is confident that the
best management practices are good for the proposed gravel operation. Ms. Weber said that given the current
practices on the storage site, there are concerns about the validity of the
best management practices for the proposed site. Mr. Fraser suggested that Mr. Ballou could take that up with FWW management. Currently, a 12 to 18 inch berm protects the wetland from the storage area.
Ms. Galloway-Leclerc said the storage yard is
there by a special exception, so the property is already subject to that
permit. The new project is related to
the existing one, and perhaps it could be looked at as one interrelated
area. They are too closely related to be
viewed as two separate projects. Ms.
Mansouri asked if she was proposing to amalgamate the two? Ms. Weber thought they were comparing apples
and oranges. The special exception is a
separate question. Ms. Mansouri said
that questions about truck traffic and the road were raised when the special
exception was granted.
Ms. Frankiewicz
expressed concern that this project will escalate and will not be considered on
a one by one basis. Mr. Britton noted we
can only address the project on the table before us. Ms. Weber emphasized the need to look at the
special exception as a separate matter.
Ms. Lundgren said that one’s home is not always tidy, but one cleans it
up for company. The site has rubber. Old
equipment, crushed buckets with no labels and a salter-type
device on it. It might have been tidied
up for the site visit. This is a
reflection of management practices for the present and the future. Ms. Frankiewicz
asked once a permit is issued, is there more notice given if FWW comes back to
do more things? Ms. Weber said that new
notice must be given to the abutters if there is an expanded use on the site or
if the project is going to continue after the permit expires. Ms. Lundgren asked if the Board was going to
consider compliance with the special exception first. Ms. Mansouri said that the gravel pit is a
separate issue. The special exception
can be taken up at the next meeting.
Thomas Fitzgerald said the gravel pit is a separate operation, but it
will use the existing road, so is that a change of the existing special
exception? Is there a new site plan? FWW
is mixing the two sites together already.
Ms. Galloway-Leclerc agreed. Mr.
Fraser said that the town regulations include earth excavations as a permitted
use. The egress is part of the site
plan. He was asked if the road is part
of the project area for the proposed operation.
He said it was an existing road, and the project will use already
existing infrastructure. Mr. Britton
said that roads used to access farm fields do not need a permit.
Mr. Lundren returned to
the issue of impact on the primary wetland, as water will flow between the two
sites. Mr. Calhoun asked if there is any
testing on water quality in the wetlands.
Mr. Palmiatto said there was not, that a hydrologist
was needed to determine water quality, and address erosion, siltation
and mitigation. Mr. Fraser said that berms are already in place and have been for years. Mr. Webb asked if it was possible to quantify
impact to say how much is detrimental.
Mr. Palmiatto said no, that needs the state
hydrologist. Mr. Webb said that the
Conservation Commission is proposing this be done. A state permit would evaluate the project and
set up mitigation measures and issue a permit.
A simple phone call could help sort out the relative impact.
Ms. Weber returned to the issue of the
road. Does the use of the road require
it to be included in the project area for purposes of determining whether a
state excavation permit is needed? Mr.
Fraser said that 2.3 acres is the threshold for a state excavation permit. Including the surface area of the road would
not bring the total area up to this. Mr.
Calhoun asked if the existing road is already having an impact on the
wetlands. Mr. Palmiatto
said the road may be lower and tipped away from the wetland so it does not look
like it would affect the wetland. He is
not confidant that best management practices would totally mitigate future
effects, but the state, not the Conservation Commission, has the authority to regulate. Mr. Shelley said the Conservation Commission
is just advisory. They turn to the state
for expertise. Ms. Galloway-Leclerc said
that we need to find out from the state if a permit is required. Mr. Lundgren asked if the Board is now
considering the special exception and the proposed excavation together or separately. Ms. Mansouri said they are still two separate
issues, and we need to find the answer.
Mr. Britton asked Mr. Fraser if the project could be done without using
the road which is close to the wetland.
Mr. Fraser said he would like to show Mr. Palmiatto
what is there now. There is a berm, a silt fence and vegetation to protect the wetland. Best management practices are in place. A new road could be constructed through the
cornfield, but that would have more impact than the current proposal. This application was submitted to the
Conservation Commission at the same time it was submitted to the ZBNA—he wishes
they had spoken up earlier. Is this the
result of outside influences? Mr. Shelley
said he learned of the site visit yesterday, and there has been no outside
influence. John Sheldon asked if the size of the project was limited because of
the wetlands and the road, and if they wanted it to get bigger later, could it? Mr. Fraser reiterated that he had been
approached by FWW for the project because of the Alstead road restoration
project. The project was sized so as not
to need a state site specific excavation permit, as those permits are out about
120 days. The project was sized for the
Alstead project and the town permit. Looking at the delineation of soils on the
plan sheet, the sand and gravel is underlain by haven soil. The wetlands cannot be excavated. Other soils in the cornfield are not as
good. There may be more gravel available
elsewhere. Ms. Weber reminded that if
the project expands, or lasts more than three years, an
new permit or an amendment will be required, either of which would require new
notice to the abutters. Mr. Sheldon
asked if FWW could apply for a new one-acre permit in three years. Ms. Mansouri said they could, but notice
would have to be given.
Ms. Weber returned to the road question. She asked if the access road was typically
included in a project area? Mr. Fraser replied that typically, it was, but
here the road already exists. Ms. Weber
asked if the special exception already in place on the property extended to
this use of the road? Ms. Galloway–Leclerc
said the special exception was solely for the storage of equipment. She doesn’t know if this will be a
substantial change difference. Mr.
Fraser said they are two separate projects.
With respect to the gravel excavation, if you grant the permit you are
granting access. Ms. Mansouri said you
are if the access was part of the project.
Mr. Calhoun said we need to determine if the road is part of the current
project. Ms. Mansouri said that might
lead to the need for a state permit. Ms.
Weber said she said that she saw two separate issues. If the existing road is being used for this
project, then the special exception already on the property should be amended
to include the change in use of the road, which was built for the storage of
construction materials and equipment. If
a new road is to be built, no special exception is required, but the road
should be included in the total project area.
Mr. Carignan said that if a new road was used, it might be required to
have a curb cut, or is a driveway allowed?
Ms. Mansouri said that would be a matter for the selectmen and the road
agent. We need to determine if the
special exception needs to be amended.
Mr. Fraser asked if the Board was saying a special exception was needed
for the road? Ms. Mansouri said that if the existing road
was permitted as a special exception, it may need to be amended. Mr. Fraser said that a legal opinion was the
way to go. A discussion followed as to
the size of the road. Mr. Fraser said if
the road is 620 feet by 20 feet and that is added onto the project area, it
still does not trigger the need for a state excavation permit.
Mr. Sisson asked if the road is part of the
special exception, how do you amend the special
exception. Ms. Weber said that a
petition would have to be filed to amend the special exception, because the use
of the road was no longer the use that had been granted in the special
exception. Mr. Sisson talked about a
special exception process he was involved in for a road over a stream. Ms. Galloway-Leclerc said that this special
exception was for the land use which required a special exception in the
Rural-Agricultural District. Ms.
Galloway-Leclerc moved that we obtain a legal opinion as to whether the
existing special exception needs to be amended because of the changed use of
the road, and also whether state permits are required because of the proximity
of the wetland. Mr. Calhoun seconded the
motion, and all voting members unanimously agreed.
The Board turned to the question of when to
reconvene the hearing. Ms. Weber said
that the regulations refer to a 20 day decision making period, but that this
hearing had already been rescheduled at the request of the applicant, so we
need to make all deliberate speed. The hearing will reconvene on Tuesday,
October 9th, at 1:30 pm in the Town Hall. The public hearing was continued to that date
at 8:55 pm.
Mr. Britton and Mr. Carignan resumed their
seats as voting members, and Mr. Webb and Mr. Calhoun returned to the alternate
seats.
NEW BUSINESS: E & W Salvage,
Chamberlain Machine by Gary Kenyon, Esq., Special Exception,
Map 14. Lot 4, Former Hubbard Farms property, west side of Route 12. Atty. Kenyon, accompanied by Chris Miller, Scott Boynton and Steve
Brackett on behalf of Chamberlain Machine, presented a binder with the
application and supporting documents and photos, and gave an overview of the
proposed project. The former Hubbard
Farms property is currently owned by Toby Tounsley,
who is subdividing the property. Bensonwood is looking at the 32 acres to the north. Chamberlain is interested in the 12.15 acre
parcel to the south. Six buildings on
the site are now or have been in the past used for hatchery operations.
Chamberlain has been in business in
Atty. Kenyon asked for the Board’s input
regarding the application. The
application was submitted as a Special Exception, but might be an expansion of
a non-conforming use. Mr. Webb explained
that because the property was used for raising chickens, it had always been
deemed to be an agricultural use. Best
to start from scratch with a special exception, as the other use has been
terminated. Mr. Kenyon said that two
coops are still in use, as is a biohazard lab used for dissection and biohazard
control. These are on the 32 acre
lot. Ms. Weber moved that the
application be treated as a Special Exception.
Ms. Galloway-Leclerc seconded and all voted in favor.
Ms. Mansouri inquired further about the mixed
use near the current plant in
Ms. Galloway-Leclerc moved that the
application be accepted and set for hearing at the regular meeting of the Board
on Wednesday, October 17. Mr. Britton seconded, and all voted in favor.
A
site visit was scheduled at the current Chamberlain Machine plant in
The public hearing will take place at the
Town Hall on October 17th at 7:30 pm.
OLD BUSINESS Robin
Casey of KC Signs for Walgreens sign replacement. Ms. Casey submitted drawings for the record of the signs which will
replace the existing Rite-Aid signs at the Walgreen’s property on Route 12. The signs will cover tha
same area as the old signs.
Gravel
Pit Educational Session will
be held at the Town Hall on October 9th. Registration is $10. Please contact
Fall
Planning and Zoning Conference
will be held at
Gravel
Pit Inspection assignments will be put off until after the educational
session on October 9th.
Minutes: Corrections to typographical
errors were submitted, and the Minutes of August 19th were moved,
seconded and unanimously approved with those changes.
The meeting was adjourned at 9:35 PM. The
next regular meeting will be held on Wednesday, 17 October, 2007 at 7:30 PM. The Board will also meet at 1:30 on October 9th
for the continuation of the Frank W. Whitcomb Corp. gravel excavation hearing.
Respectfully
submitted,
Lucy Weber,
Secretary.